The MOST important reason for developing and monitoring key risk indicators (KRIs) is that they provide:

A.

measurable metrics for acceptable risk levels.

Answers
A.

measurable metrics for acceptable risk levels.

B.

information about control compliance.

Answers
B.

information about control compliance.

C.

an early warning of possible risk materialization.

Answers
C.

an early warning of possible risk materialization.

Suggested answer: C

Explanation:

Step by Step Comprehensive Detailed Explanation with All

Reference:

Purpose of KRIs:

KRIs are designed to provide early warnings about potential risk events.

They help organizations to take preventive actions before risks become critical issues.

Early Warning System:

KRIs are critical for proactive risk management, enabling organizations to respond quickly to changes in risk levels.

They complement other risk management tools by focusing on early detection.

ISA 315 (Revised 2019), Anlage 5 discusses the importance of timely and accurate information in managing and mitigating risks effectively.

asked 18/11/2024
George Sanchez
38 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first