ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 162 - HPE0-J68 discussion

Report
Export

A customer currently has a CS1000H and wants to upgrade to a CS3000.

What must be considered before upgrading?

A.
This upgrade is disruptive and needs planned downtime.
Answers
A.
This upgrade is disruptive and needs planned downtime.
B.
A capacity upgrade to a fully populated array has to be performed first.
Answers
B.
A capacity upgrade to a fully populated array has to be performed first.
C.
Timeless storage support is not offered for CS1000H entry-level systems.
Answers
C.
Timeless storage support is not offered for CS1000H entry-level systems.
D.
A controller upgrade to a CS1000F has to be performed first.
Answers
D.
A controller upgrade to a CS1000F has to be performed first.
Suggested answer: A

Explanation:

Upgrading from a HPE Nimble Storage CS1000H to a CS3000 involves a disruptive upgrade process, meaning that planned downtime will be required. The disruption occurs because such an upgrade involves significant changes to the storage system, including hardware replacements and potentially data migration, which cannot be performed while the system is online.

Proper planning and scheduling of the downtime are essential to minimize the impact on business operations.

For more details, refer to:

HPE Nimble Storage Overview

asked 16/09/2024
Lakshmana Mittadoddi
39 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first