Question 210 - HPE0-V14 discussion
You are installing a server solution in a customer's data center.
How can you ensure that the installation complies with relevant electrical best practices? (Choose two.)
A.
Use a single-phase, two-wire power receptacle with protective earth or ground (PE) to filter interference from the power grid
B.
Do not allow the overall system AC current load to exceed 80% of the branch circuit AC current rating
C.
Use fanout cables when connecting the server to the network for maximum electrical impedance
D.
Balance the server power load between available AC supply branch circuits
E.
Configure the server power to a single electrical circuit in the data center