When preparing a site for an ACP 4200 installation, which task is optional?

A.
Identify potential obstacles, such as signs and fire extinguishers in the path from the delivery location to the permanent site.
Answers
A.
Identify potential obstacles, such as signs and fire extinguishers in the path from the delivery location to the permanent site.
B.
Plan the path from the delivery location to the permanent site.
Answers
B.
Plan the path from the delivery location to the permanent site.
C.
Ensure that a minimum of four people are available to move the ACP 4200 due to its size and weight.
Answers
C.
Ensure that a minimum of four people are available to move the ACP 4200 due to its size and weight.
D.
Ensure there is a room to maneuver the ACP 4200 around any tight corners in hallways.
Answers
D.
Ensure there is a room to maneuver the ACP 4200 around any tight corners in hallways.
Suggested answer: A