Examine the following Blue Prism Process diagram:

The initial values of the data items are displayed in the diagram above All 3 data items are configured as Number

The 'Perform Calculation' stage Properties window is displayed below:

When this diagram is run through the the End stage, what will the current value of the Z data item be?

A.
-1
Answers
A.
-1
B.
[X]*[Y]
Answers
B.
[X]*[Y]
C.
An Internal Exception will be thrown as the Expression contains multiple blank spaces
Answers
C.
An Internal Exception will be thrown as the Expression contains multiple blank spaces
D.
0
Answers
D.
0
E.
12
Answers
E.
12
Suggested answer: E

Explanation:

The calculation stage will assign the value of [X][Y] to the Z data item, which is 34 = 12.The blank spaces in the expression do not affect the calculation1.

Reference:1https://bpdocs.blueprism.com/bp-6-9/en-us/frmStagePropertiesCalculation.htm