Question 23 - ASDEV01 discussion
Examine the following Blue Prism Process diagram:
The initial values of the data items are displayed in the diagram above All 3 data items are configured as Number
The 'Perform Calculation' stage Properties window is displayed below:
When this diagram is run through the the End stage, what will the current value of the Z data item be?
A.
-1
B.
[X]*[Y]
C.
An Internal Exception will be thrown as the Expression contains multiple blank spaces
D.
0
E.
12