Question 50 - ASDEV01 discussion
Which of the following statements best describes an Exception Retry within a Work Queue?
A.
An Item that has been marked as Complete' after processing, is then reworked by the Process as if it were a new pending Item
B.
When an Item that has been marked as 'Exception* after processing, is then sent to the manual team for review
C.
When an Item that has been marked as 'Complete* after processing is then sent to the manual team for review
D.
An Item that has been marked as 'Exception' after processing, is then reworked by the Process as if it were a new pending Item