Which of the following statements best describes an Exception Retry within a Work Queue?

A.
An Item that has been marked as Complete' after processing, is then reworked by the Process as if it were a new pending Item
Answers
A.
An Item that has been marked as Complete' after processing, is then reworked by the Process as if it were a new pending Item
B.
When an Item that has been marked as 'Exception* after processing, is then sent to the manual team for review
Answers
B.
When an Item that has been marked as 'Exception* after processing, is then sent to the manual team for review
C.
When an Item that has been marked as 'Complete* after processing is then sent to the manual team for review
Answers
C.
When an Item that has been marked as 'Complete* after processing is then sent to the manual team for review
D.
An Item that has been marked as 'Exception' after processing, is then reworked by the Process as if it were a new pending Item
Answers
D.
An Item that has been marked as 'Exception' after processing, is then reworked by the Process as if it were a new pending Item
Suggested answer: D

Explanation:

This is the correct definition of an exception retry within a work queue. It allows the process to attempt to process the item again after resolving the exception. The other options are either incorrect or describe different scenarios.

Reference: https://portal.blueprism.com/sites/default/files/2021-05/Blue%20Prism%20Certification%20-%20Associate%20Developer%20-%20Certification%20Overview_0.pdf (page 16)

asked 16/09/2024
David Tirado
29 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first