Question 469 - CLF-C02 discussion
A company wants to migrate a database from an on-premises environment to Amazon RDS.
After the migration is complete, which management task will the company still be responsible for?
A.
Hardware lifecycle management
B.
Application optimization
C.
Server maintenance
D.
Power, network, and cooling provisioning
Your answer: