An organization plans to connect three different sites over IP using a RecoverPoint cluster at each site. However, the cluster fails to connect. The network team has determined that the required IP routing and WAN connectivity is in place. The desired routing information is added while running the Deployment Manager wizard.
What is a possible cause for the failure?
A.
Secondary sites are on different network subnets
B.
Jumbo frames are not enabled on the IP network
C.
MTU size is to be set to 9000
D.
boxmgmt password is different at the secondary sites