ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 37 - 312-38 discussion

Report
Export

Which of the following recovery plans includes specific strategies and actions to deal with specific variances to assumptions resulting in a particular security problem, emergency, or state of affairs?

A.
Contingency plan
Answers
A.
Contingency plan
B.
Disaster recovery plan
Answers
B.
Disaster recovery plan
C.
Business continuity plan
Answers
C.
Business continuity plan
D.
Continuity of Operations Plan
Answers
D.
Continuity of Operations Plan
Suggested answer: A

Explanation:

A contingency plan is a plan devised for a specific situation when things could go wrong. Contingency plans are often devised by governments or businesses who want to be prepared for anything that could happen. Contingency plans include specific strategies and actions to deal with specific variances to assumptions resulting in a particular problem, emergency, or state of affairs. They also include a monitoring process and "triggers" for initiating planned actions. They are required to help governments, businesses, or individuals to recover from serious incidents in the minimum time with minimum cost and disruption.

Answer option D is incorrect. It includes the plans and procedures documented that ensure the continuity of critical operations during any period where normal operations are impossible.

Answer option B is incorrect. Disaster recovery planning is a subset of a larger process known as business continuity planning and should include planning for resumption of applications, data, hardware, communications (such as networking), and other IT infrastructure. A business continuity plan (BCP) includes planning for non-IT related aspects such as key personnel, facilities, crisis communication, and reputation protection, and should refer to the disaster recovery plan (DRP) for IT-related infrastructure recovery/continuity.

Answer option C is incorrect. Business continuity planning (BCP) is the creation and validation of a practiced logistical plan for how an organization will recover and restore partially or completely interrupted critical (urgent) functions within a predetermined time after a disaster or extended disruption. The logistical plan is called a business continuity plan. The BCP lifecycle is as follows:

asked 18/09/2024
John Doe
36 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first