What is the technique used in the cost estimates for the project during the design phase of the following? Each correct answer represents a complete solution.

Choose all that apply.

A.
expert assessment
Answers
A.
expert assessment
B.
The Delphi technique
Answers
B.
The Delphi technique
C.
Function point analysis
Answers
C.
Function point analysis
D.
Program Evaluation Technique (PERT)
Answers
D.
Program Evaluation Technique (PERT)
Suggested answer: A, B, C