After a risk assessment is performed, a particular risk is considered to have the potential of costing the organization 1.2 Million USD. This is an example of

A.
Risk Tolerance
Answers
A.
Risk Tolerance
B.
Qualitative risk analysis
Answers
B.
Qualitative risk analysis
C.
Risk Appetite
Answers
C.
Risk Appetite
D.
Quantitative risk analysis
Answers
D.
Quantitative risk analysis
Suggested answer: D