When choosing a risk mitigation method what is the MOST important factor?

A.
Approval from the board of directors
Answers
A.
Approval from the board of directors
B.
Cost of the mitigation is less than the risk
Answers
B.
Cost of the mitigation is less than the risk
C.
Metrics of mitigation method success
Answers
C.
Metrics of mitigation method success
D.
Mitigation method complies with PCI regulations
Answers
D.
Mitigation method complies with PCI regulations
Suggested answer: B