You work as a project manager for TYU project. You are planning for risk mitigation. You need to quickly identify high-level risks that will need a more in-depth analysis. Which of the following activities will help you in this?
A.
Qualitative analysis
B.
Quantitative analysis
C.
Risk mitigation
D.
Estimate activity duration