Which of the following is the BEST indicator of a successful project?
A.
it is completed on time or early as compared to the baseline project plan
B.
it meets most of the specifications as outlined in the approved project definition
C.
it comes in at or below the expenditures planned for in the baseline budget
D.
the deliverables are accepted by the key stakeholders