In the information security system construction management cycle, which of the following behaviors is "check" What needs to be implemented in the link?

A.
Safety management system design
Answers
A.
Safety management system design
B.
Safety management system implementation
Answers
B.
Safety management system implementation
C.
Risk assessment
Answers
C.
Risk assessment
D.
Safety management system operation monitoring
Answers
D.
Safety management system operation monitoring
Suggested answer: C