Which of the following is the correct power-on sequence of the Huawei OceanStor 9000 big data storage system?
A.
Cabinet-->Switch-->KVM--->Node
B.
Cabinet-->KVM-->Switch--->Node
C.
Cabinet-->Switch-->Node--->KVM
D.
Cabinet-->Node-->KVM--->Switch