Applying ISO 31000, which of the following is part of the external context for risk management?

A.
Risk treatment method based on risk evaluation.
Answers
A.
Risk treatment method based on risk evaluation.
B.
Organizational culture, objectives, and processes.
Answers
B.
Organizational culture, objectives, and processes.
C.
The regulatory and competitive environment
Answers
C.
The regulatory and competitive environment
D.
The method of determining the risk level.
Answers
D.
The method of determining the risk level.
Suggested answer: C