Question 127 - IIA-CIA-Part1 discussion
Which of the following is an example of risk monitoring to ensure a system is performing as intended?
A.
Checking the progress of risk treatment plans
B.
Considering the consequence and likelihood of risks
C.
Documenting the risks and their areas of impact
D.
Communicating to management about risks