Which of the following actions would best help the internal audit activity promote continuous improvement in control effectiveness within the organization?

A.
Determining whether management measures and monitors the costs and benefits of controls.
Answers
A.
Determining whether management measures and monitors the costs and benefits of controls.
B.
Providing training on controls and ongoing self-monitoring processes.
Answers
B.
Providing training on controls and ongoing self-monitoring processes.
C.
Developing flowcharts to obtain information about control design adequacy.
Answers
C.
Developing flowcharts to obtain information about control design adequacy.
D.
Identifying objectives and the risks involved in achieving them.
Answers
D.
Identifying objectives and the risks involved in achieving them.
Suggested answer: B