Which of the following is an indicator that an organization's risk management processes are effective?

A.
Departmental objectives are managed by department heads and are independent of the organization's mission.
Answers
A.
Departmental objectives are managed by department heads and are independent of the organization's mission.
B.
Organization wide mechanisms exist to enable the identification and assessment of all significant risks.
Answers
B.
Organization wide mechanisms exist to enable the identification and assessment of all significant risks.
C.
Department heads have the autonomy to determine risk responses that fall outside of the organizations risk appetite
Answers
C.
Department heads have the autonomy to determine risk responses that fall outside of the organizations risk appetite
D.
Relevant risk information is captured and communicated primarily between management and the board
Answers
D.
Relevant risk information is captured and communicated primarily between management and the board
Suggested answer: B