When creating the internal audit plan, the chief audit executive should prioritize engagements based primarily on which of the following?

A.
The last available risk assessment.
Answers
A.
The last available risk assessment.
B.
Requests from senior management and the board.
Answers
B.
Requests from senior management and the board.
C.
The longest interval since the last examination of each audit universe item.
Answers
C.
The longest interval since the last examination of each audit universe item.
D.
The auditable areas required by regulatory agencies.
Answers
D.
The auditable areas required by regulatory agencies.
Suggested answer: A

Explanation:

The IIA Standards emphasize that the chief audit executive (CAE) should develop the internal audit plan based on a thorough assessment of risks facing the organization. This risk-based approach ensures that the most significant and relevant areas are prioritized. While input from senior management and regulatory requirements are also important, the primary driver should be the most recent and comprehensive risk assessment.

Reference:

IIA Standards - 2010: Planning

IIA Practice Guide - Developing the Risk-based Internal Audit Plan

asked 18/09/2024