List of questions
Related questions
Question 154 - IIA-CIA-Part2 discussion
An internal auditor completed a review of expenses related to the launch of a new project. The auditor sampled 45 transactions approved by a senior project manager and identified 30 with questionable vendor documentation. Which of the following is the most appropriate conclusion for the auditor to include in the audit report?
A.
The organization incurred excessive cost overruns that resulted in significant financial and legal risk to the project.
B.
The organization experienced a potential conflict of interest
C.
The organization had weaknesses in its review process which allowed questionable transactions with some vendors
D.
The organization allowed the project to launch without assurance that all transactions were regularly approved
Your answer:
0 comments
Sorted by
Leave a comment first