An internal audit manager is planning a contract compliance audit Which of the following should be done prior to developing the audit work program?

A.
Select a sample of invoices for substantive testing
Answers
A.
Select a sample of invoices for substantive testing
B.
Review the contract for evidence of authorization
Answers
B.
Review the contract for evidence of authorization
C.
Document underlying reasons for noncompliance
Answers
C.
Document underlying reasons for noncompliance
D.
Assess the inherent risk of paying duplicate invoices
Answers
D.
Assess the inherent risk of paying duplicate invoices
Suggested answer: B

Explanation:

Before developing the audit work program, it is essential to review the contract for evidence of authorization. This step ensures that the contract is valid and approved by the appropriate parties, forming a critical basis for the compliance audit. By confirming authorization, the auditor can ascertain that the contract is legitimate and enforceable, and understand its key terms and conditions, which is necessary for planning and executing the audit effectively. Other steps, such as selecting a sample or assessing risks, are important but should follow after understanding the contract's validity and scope.

Reference:

Institute of Internal Auditors (IIA), International Standards for the Professional Practice of Internal Auditing (Standards), Standard 2201 -- Planning Considerations.

asked 18/09/2024
shaoyu huang
28 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first