An internal audit team leader is having difficulties completing the planning phase of an assurance engagement because the business unit lacks a system of internal controls. Which of the following is the most appropriate course of action for the internal audit team leader?
A.
Defer the engagement until a system of internal control has been established
B.
Change the scheduled engagement from assurance to consulting to help correct the shortcomings
C.
Add a consulting component to the already scheduled assurance engagement
D.
Seek the involvement of the external auditor to assist with improving the internal controls