Question 373 - IIA-CIA-Part2 discussion
Which of the following internal audit activities is performed in the design evaluation phase?
A.
The internal auditor reviews prior audits and workpapers.
B.
The internal auditor identifies the controls over segregation of duties.
C.
The internal auditor checks a process for completeness.
D.
The internal auditor communicates the audit results to management.
Your answer: