Management has learned the implementation of a new IT system will not be completed on time and has requested an audit. Which of the following audit findings should be of GREATEST concern?
A.
The actual start times of some activities were later than originally scheduled.
B.
Tasks defined on the critical path do not have resources allocated.
C.
The project manager lacks formal certification.
D.
Milestones have not been defined for all project products.