A system development project is experiencing delays due to ongoing staff shortages. Which of the following strategies would provide the GREATEST assurance of system quality at implementation?
A.
Implement overtime pay and bonuses for all development staff.
B.
Utilize new system development tools to improve productivity.
C.
Recruit IS staff to expedite system development.
D.
Deliver only the core functionality on the initial target date.