A system development project is experiencing delays due to ongoing staff shortages. Which of the following strategies would provide the GREATEST assurance of system quality at implementation?

A.
Implement overtime pay and bonuses for all development staff.
Answers
A.
Implement overtime pay and bonuses for all development staff.
B.
Utilize new system development tools to improve productivity.
Answers
B.
Utilize new system development tools to improve productivity.
C.
Recruit IS staff to expedite system development.
Answers
C.
Recruit IS staff to expedite system development.
D.
Deliver only the core functionality on the initial target date.
Answers
D.
Deliver only the core functionality on the initial target date.
Suggested answer: D

Explanation:

The strategy that would provide the greatest assurance of system quality at implementation is delivering only the core functionality on the initial target date. This strategy can help avoid compromising the quality of the system by focusing on the essential features that meet the user needs and expectations. Delivering only the core functionality can also help reduce the scope creep, complexity, and testing efforts of the system development project.

Implementing overtime pay and bonuses for all development staff, utilizing new system development tools to improve productivity, and recruiting IS staff to expedite system development are not strategies that would provide the greatest assurance of system quality at implementation. These strategies may help speed up the system development process, but they may also introduce new risks or challenges such as burnout, learning curve, integration issues, or communication gaps. These risks or challenges may adversely affect the quality of the system.