Question 199 - CISA discussion
The due date of an audit project is approaching, and the audit manager has determined that only 60% of the audit has been completed. Which of the following should the audit manager do FIRST?
A.
Determine where delays have occurred
B.
Assign additional resources to supplement the audit
C.
Escalate to the audit committee
D.
Extend the audit deadline