Which of the following occurs during the issues management process for a system development project?

A.
Contingency planning
Answers
A.
Contingency planning
B.
Configuration management
Answers
B.
Configuration management
C.
Help desk management
Answers
C.
Help desk management
D.
Impact assessment
Answers
D.
Impact assessment
Suggested answer: D

Explanation:

Impact assessment is an activity that occurs during the issues management process for a system development project. Issues management is a process of identifying, analyzing, resolving, and monitoring issues that may affect the project scope, schedule, budget, or quality. Impact assessment is a technique of evaluating the severity and priority of an issue, as well as its implications for the project objectives and deliverables. The other options are not activities that occur during the issues management process, but rather related to other processes such as contingency planning, configuration management, or help desk management.Reference:

CISA Review Manual (Digital Version), Chapter 4, Section 4.3.31