During an IT general controls audit of a high-risk area where both internal and external audit teams are reviewing the same approach to optimize resources?
A.
Leverage the work performed by external audit for the internal audit testing.
B.
Ensure both the internal and external auditors perform the work simultaneously.
C.
Request that the external audit team leverage the internal audit work.
D.
Roll forward the general controls audit to the subsequent audit year.