Question 479 - CISA discussion
Which of the following is the MOST appropriate indicator of change management effectiveness?
A.
Time lag between changes to the configuration and the update of records
B.
Number of system software changes
C.
Time lag between changes and updates of documentation materials
D.
Number of incidents resulting from changes