In which of the following system development life cycle (SDLC) phases would an IS auditor expect to find that controls have been incorporated into system specifications?

A.
Implementation
Answers
A.
Implementation
B.
Development
Answers
B.
Development
C.
Feasibility
Answers
C.
Feasibility
D.
Design
Answers
D.
Design
Suggested answer: D

Explanation:

The design phase of the system development life cycle (SDLC) is where an IS auditor would expect to find that controls have been incorporated into system specifications, because this is where the system requirements are translated into detailed design specifications that include the technical, functional, and security aspects of the system34.The implementation phase is where the system is deployed and tested, the development phase is where the system is coded and unit tested, and the feasibility phase is where the system objectives and scope are defined.Reference:3: CISA Review Manual (Digital Version), Chapter 4, Section 4.2.24: CISA Online Review Course, Module 4, Lesson 2

asked 18/09/2024
Yuriy Kitsis
35 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first