A new system development project is running late against a critical implementation deadline Which of the following is the MOST important activity?

A.
Document last-minute enhancements
Answers
A.
Document last-minute enhancements
B.
Perform a pre-implementation audit
Answers
B.
Perform a pre-implementation audit
C.
Perform user acceptance testing (UAT)
Answers
C.
Perform user acceptance testing (UAT)
D.
Ensure that code has been reviewed
Answers
D.
Ensure that code has been reviewed
Suggested answer: C

Explanation:

Performing user acceptance testing (UAT) is the most important activity before implementing a new system, as it ensures that the system meets the user requirements and expectations, and that it is free of major defects.Documenting last-minute enhancements, performing a pre-implementation audit, and ensuring that code has been reviewed are also important activities, but they are not as critical as UAT.Reference:CISA Review Manual (Digital Version), Chapter 4, Section 4.2.2