Which of the following is MOST appropriate to review when determining if the work completed on an IT project is in alignment with budgeted costs?

A.
Return on investment (ROI) analysis
Answers
A.
Return on investment (ROI) analysis
B.
Earned value analysis (EVA)
Answers
B.
Earned value analysis (EVA)
C.
Financial value analysis
Answers
C.
Financial value analysis
D.
Business impact analysis (BIA)
Answers
D.
Business impact analysis (BIA)
Suggested answer: B

Explanation:

EVA is a project management technique that measures the performance of a project by comparing the actual work completed, the actual costs incurred, and the planned costs for the work scheduled. EVA can help determine if the project is on track, ahead of schedule, or behind schedule, and if the project is under budget, over budget, or on budget. EVA can also help forecast the final cost and schedule of the project based on the current performance.

Reference

ISACA CISA Review Manual, 27th Edition, page 255

18. Project Completion -- Project Management -- 2nd Edition

How to Measure Project Success | Smartsheet

asked 18/09/2024
Ali Diaz
31 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first