Which of the following is a PRIMARY benefit of using risk assessments to determine areas to be included in an audit plan?

A.
Timely audit execution
Answers
A.
Timely audit execution
B.
Effective allocation of audit resources
Answers
B.
Effective allocation of audit resources
C.
Reduced travel and expense costs
Answers
C.
Reduced travel and expense costs
D.
Effective risk mitigation
Answers
D.
Effective risk mitigation
Suggested answer: B

Explanation:

Using risk assessments to determine areas to be included in an audit plan is a primary benefit because it helps to prioritize the audit activities based on the level of risk and the potential impact of the audit findings. This way, the audit resources, such as time, staff, and budget, can be allocated more efficiently and effectively to the areas that need the most attention and provide the most value.

Reference

ISACA CISA Review Manual, 27th Edition, page 256

What is the Purpose of a Risk Assessment?

Mastering the Process of Risk Assessment

asked 18/09/2024
Dimitar Krachunov
31 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first