If a recent release of a program has to be backed out of production, the corresponding changes within the delta version of the code should be:

A.
filed in production for future reference in researching the problem.
Answers
A.
filed in production for future reference in researching the problem.
B.
applied to the source code that reflects the version in production.
Answers
B.
applied to the source code that reflects the version in production.
C.
eliminated from the source code that reflects the version in production.
Answers
C.
eliminated from the source code that reflects the version in production.
D.
reinstalled when replacing the version back into production.
Answers
D.
reinstalled when replacing the version back into production.
Suggested answer: C

Explanation:

When a program release needs to be backed out of production, the changes introduced by that release must be removed from the source code to ensure the system returns to its prior state. This approach ensures that the source code reflects the stable version without the problematic changes.

Reference

ISACA CISA Review Manual 27th Edition, Page 244-245 (Change Management)