List of questions
Related questions
Question 756 - CISA discussion
Which of the following should be the GREATEST concern for an IS auditor performing a post-implementation review for a major system upgrade?
A.
Changes are promoted to production by the development group.
B.
Object code can be accessed by the development group.
C.
Developers have access to the testing environment.
D.
Change approvals are not formally documented.