A new system development project is running late against a critical implementation deadline. Which of the following is the MOST important activity?

A.
Ensure that code has been reviewed.
Answers
A.
Ensure that code has been reviewed.
B.
Perform user acceptance testing (UAT).
Answers
B.
Perform user acceptance testing (UAT).
C.
Document last-minute enhancements.
Answers
C.
Document last-minute enhancements.
D.
Perform a pre-implementation audit.
Answers
D.
Perform a pre-implementation audit.
Suggested answer: B