Question 814 - CISA discussion
Which of the following is the MAIN risk associated with adding a new system functionality during the development phase without following a project change management process?
A.
The project may go over budget.
B.
The added functionality has not been documented.
C.
The project may fail to meet the established deadline.
D.
The new functionality may not meet requirements.
Your answer: