Which of the following is the MOST appropriate responsibility of an IS auditor involved in a data center renovation project?
A.
Performing independent reviews of responsible parties engaged in the project
B.
Shortlisting vendors to perform renovations
C.
Ensuring the project progresses as scheduled and milestones are achieved
D.
Implementing data center operational controls