Which of the following would BEST guide an IS auditor when determining an appropriate time to schedule the follow-up of agreed corrective actions for reported audit issues?

A.
Progress updates indicate that the implementation of agreed actions is on track.
Answers
A.
Progress updates indicate that the implementation of agreed actions is on track.
B.
Sufficient time has elapsed since implementation to provide evidence of control operation.
Answers
B.
Sufficient time has elapsed since implementation to provide evidence of control operation.
C.
Business management has completed the implementation of agreed actions on schedule.
Answers
C.
Business management has completed the implementation of agreed actions on schedule.
D.
Regulators have announced a timeline for an inspection visit.
Answers
D.
Regulators have announced a timeline for an inspection visit.
Suggested answer: B

Explanation:

This is because the follow-up of agreed corrective actions for reported audit issues should be done after the auditee has had enough time to implement the corrective actions and demonstrate their effectiveness and sustainability.The follow-up audit should not be too soon or too late, but based on a reasonable and realistic timeframe that allows for adequate testing and verification of the control operation12.

Answer A. Progress updates indicate that the implementation of agreed actions is on track. is not the best answer, because progress updates are not sufficient to guide the follow-up audit timing. Progress updates are useful for monitoring and communicating the status and challenges of the corrective actions, but they do not provide conclusive evidence of the control operation.The follow-up audit should be based on actual results and outcomes, not on expectations or projections12.

Answer C. Business management has completed the implementation of agreed actions on schedule. is not the best answer, because the completion of the implementation of agreed actions is not enough to guide the follow-up audit timing. The completion of the implementation only indicates that the auditee has taken the necessary steps to address the audit issues, but it does not guarantee that the corrective actions are effective and sustainable.The follow-up audit should be based on the evaluation and validation of the control operation, not on the completion of the control implementation12.

Answer D. Regulators have announced a timeline for an inspection visit. is not the best answer, because the regulators' inspection visit is not relevant to guide the follow-up audit timing. The regulators' inspection visit is an external factor that may or may not coincide with the internal follow-up audit schedule.The follow-up audit should be based on the internal audit plan and objectives, not on the external audit requirements or expectations12.