Which of the following techniques would be used during a risk assessment to demonstrate to stakeholders that all known alternatives were evaluated?

A.
Control chart
Answers
A.
Control chart
B.
Sensitivity analysis
Answers
B.
Sensitivity analysis
C.
Trend analysis
Answers
C.
Trend analysis
D.
Decision tree
Answers
D.
Decision tree
Suggested answer: D