A business unit is updating a risk register with assessment results for a key project. Which of the following is MOST important to capture in the register?
A.
The team that performed the risk assessment
B.
An assigned risk manager to provide oversight
C.
Action plans to address risk scenarios requiring treatment
D.
The methodology used to perform the risk assessment