Which of the following is the BEST indication of an effective risk management program?

A.
Risk action plans are approved by senior management.
Answers
A.
Risk action plans are approved by senior management.
B.
Residual risk is within the organizational risk appetite
Answers
B.
Residual risk is within the organizational risk appetite
C.
Mitigating controls are designed and implemented.
Answers
C.
Mitigating controls are designed and implemented.
D.
Risk is recorded and tracked in the risk register
Answers
D.
Risk is recorded and tracked in the risk register
Suggested answer: B