After undertaking a risk assessment of a production system, the MOST appropriate action is for the risk manager to:

A.
recommend a program that minimizes the concerns of that production system.
Answers
A.
recommend a program that minimizes the concerns of that production system.
B.
inform the development team of the concerns, and together formulate risk reduction measures.
Answers
B.
inform the development team of the concerns, and together formulate risk reduction measures.
C.
inform the process owner of the concerns and propose measures to reduce them
Answers
C.
inform the process owner of the concerns and propose measures to reduce them
D.
inform the IT manager of the concerns and propose measures to reduce them.
Answers
D.
inform the IT manager of the concerns and propose measures to reduce them.
Suggested answer: A