Question 173 - CRISC discussion
Which of the following should be the PRIMARY objective of a risk awareness training program?
A.
To enable risk-based decision making
B.
To promote awareness of the risk governance function
C.
To clarify fundamental risk management principles
D.
To ensure sufficient resources are available