Question 196 - CRISC discussion
Deviation from a mitigation action plan's completion date should be determined by which of the following?
A.
Change management as determined by a change control board
B.
Benchmarking analysis with similar completed projects
C.
Project governance criteria as determined by the project office
D.
The risk owner as determined by risk management processes