Which of the following should management consider when selecting a risk mitigation option?

A.
Maturity of the enterprise architecture
Answers
A.
Maturity of the enterprise architecture
B.
Cost of control implementation
Answers
B.
Cost of control implementation
C.
Reliability of key performance indicators (KPIs)
Answers
C.
Reliability of key performance indicators (KPIs)
D.
Reliability of key risk indicators (KPIs)
Answers
D.
Reliability of key risk indicators (KPIs)
Suggested answer: B