A risk practitioner has learned that an effort to implement a risk mitigation action plan has stalled due to lack of funding. The risk practitioner should report that the associated risk has been:

A.
mitigated
Answers
A.
mitigated
B.
accepted
Answers
B.
accepted
C.
avoided
Answers
C.
avoided
D.
deferred
Answers
D.
deferred
Suggested answer: B