Question 261 - CRISC discussion
A company has located its computer center on a moderate earthquake fault. Which of the following is the MOST important consideration when establishing a contingency plan and an alternate processing site?
A.
The alternative site is a hot site with equipment ready to resume processing immediately.
B.
The contingency plan provides for backup media to be taken to the alternative site.
C.
The contingency plan for high priority applications does not involve a shared cold site.
D.
The alternative site does not reside on the same fault to matter how the distance apart.
Your answer: